UP SODIC LANDS RECLAMATION PROJECT ( Sodic-I )
   
Name of the project

U.P. Sodic Lands Reclamation Project-I (Cr.2510 IN)

Selected Districts (10) Aligarh, Allahabad, Etah, Etawah(Auriya), Fatehpur, Mainpuri, Pratapgarh, Raebareli & Sultanpur, Harodi.
Project Period June 1993 to March 2001.
Physical Target  45,000 hq.         Revised- 68,800 hq.
Project Cost (Crore Rs.)
 
Subject

S.A.R

Revised(MTR)

State Share 51.24 51.24
World Bank (IDA) Loan 213.96 213.96
Sub Total 265.20 265.20
Farmer Share 48.5 129.96
Total Cost 313.71 395.17
 
 
Major Outputs
 
 

Economic Outputs

  • Reclamation of 68,414 ha. land out of which 36,026 ha. area brought under cultivation for the first time.

  • Cropping intensity increased from 37% to 230%

  • 208.59 lakh . Rs. loan sanctioned and disbursed for  Pumpset..

  • 721.38 lakh . Rs. loan sanctioned and disbursed for  Crop.

  • Upward revision of wage rate

  • Value of reclaimed sodic lands has increased.

  • 164.98 lakh man days created.

  • Reduction in migration from villages.

  • Increase in farm income upto 96%.

  • BPL families from 80% to 56%

  • 52% to 58% increase in rural wage rate.

Social Outputs

  • Beneficiary profile: Total 155892, SM/MF 147259 (94%), SC/ST 43586 (27%), BC 67797 (44%)

  • About 62795 beneficiaries benefited by 25366 ha. land allotment.

  • 15949 WUG formed which are functional

  • 2166 WSHG formed which saved Rs 155.54 lakhs.

  • 1618 WSHGs linked with banks and they availed Cash Credit Limit of Rs. 358.45lakhs.

  • WSHG loaned Rs. 476.54 lakhs . (Inter loaning)

Infrastructure Development

  • So far 10930 Tubewell developed and PumpSets added on these new boring  and already existing borings without pumpsets.

  • 124Tube well energised.

  • 46890 ha. additional irrigation potential created

  • 887 SIC maintenance account opened.  Amount deposited Rs. 17.28 lacs. out of which Rs. 9.12 lacs have been utilised for maintenance of Link Drains.

  • 2508 Km. Link Drain constructed.

  • 5570 Km. Field Drain constructed.

  • 2463 Km. Main Remodelled.

Institutional Development

  • Site Implementation Committee.

  • Water Users Group.

  • Women Self Help Group.

  • Development of trained manpower in project area 14,000 persons trained.

  • Technical bulletin & extension literature prepared for LDC / NGO staff  / beneficiaries.